The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. Phase 2 of the north and south abutments is underway, with an estimated completion date for the abutments being mid-October.

The proposed pedestrian tunnel is completely installed, with backfill and drainage currently being installed.

Excavation for a long mechanically stabilized earth wall at the south end of the project is uncomplete. Once drainage for this wall is installed, the wall construction will begin.