The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation.  Both the north and south abutments are complete, and pier construction will begin in the coming months.

Retaining walls on the south side of the project are underway, and the pedestrian tunnel is fully installed and backfilled.

Drainage pipe has be installed around the project as well.