The Harford Road Bridge contractor has fully completed demolition of the existing bridge.  Excavation and rock removal for the new bridge abutments and piers is underway.

Construction of the north abutment will begin in early June, followed by construction of the south abutment later in the month.

The demolition shield above Herring Run is fully removed, and stockpiled material in the project’s southeast corner will be removed in June.