The Harford Road Bridge contractor is nearly complete with demolition of the existing bridge.  The existing arches have been completely removed and the last remaining parts of concrete that were below ground are being excavated.  The rubble created by the demolition of the bridge is being pulverized and taken off site.

Rock excavation for the proposed north abutment substructure is underway.  The footing for this substructure is scheduled to be installed in mid-May.

The demolition shield above Herring Run is being removed, and stockpiled in the projects southeast corner is being removed.