The Harford Road Bridge contractor has constructed a stream diversion system to protect the pier work area from the water.  They are now gearing up to begin construction of the bridge piers near Herring Run.

The Contractor is finishing construction of the cast-in-place retaining wall on the south side of the bridge.

The Contractor also continues to backfill Abutment B.