The Harford Road Bridge Contractor has constructed the bottom half of Pier 2 and a portion of the top half. They have also started backfilling around Pier 2.
The Contractor is getting ready to dewater at the Pier 1 Stream Flow Diversion structure in order to place the Pier 1 footing.
They continue backfilling at the North Abutment and have started excavation behind the South Abutment to prepare for utility placement.