The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. The north abutment footing has been placed, and reinforcement and formwork for the abutment wall is underway. The south footing formwork and reinforcement bar have been installed and are awaiting concrete.

Excavation for the two piers has been completed and construction of the pier footings will begin in July.

Excavation for the proposed pedestrian tunnel between Chesterfield Avenue and Herring Run is underway. Footings for the pedestrian tunnel will be installed in July.