The Harford Road Bridge contractor has placed the concrete parapet along the majority of the bridge and retaining walls and is finishing up placing the curb near Chesterfield Ave. They have placed stone on the subgrade and are working toward finishing the base pavement.

The Contractor is completing placement of utilities under the bridge.

The Contractor is preparing the substructure for paint and the pedestrian tunnel has been painted.

The updated community meeting boards shown under the photos section reflect landscaping near the pedestrian tunnel and the north abutment which was revised due to the presence of rock at these locations. In these locations, boulders will be placed at the base of the slope and infilled with soil and plantings.