The Harford Road Bridge contractor is completing construction of Pier 1.

The girder erection crane has been erected. It will be used to set the girders on the new bridge. Several girders have been delivered to the site; the remaining girders are scheduled to be delivered in the next several weeks.

The Contractor continues to excavate for utilities north of the bridge.

Parking will be restricted on one side of the Herring Run Park access road for the next several weeks to accommodate girder delivery.