The Harford Road Bridge contractor continues work to pour an exterior piece of the concrete deck and the top portion of the mechanically stabilized earth (MSE) wall.

Utility construction is wrapping up on the south side of the bridge and they are starting excavation for utilities under the bridge. They are also backfilling in front of the cast-in-place retaining wall.