The Harford Road Bridge Contractor has constructed the Pier 2 footing and has started setting reinforcing steel and formwork to pour the wall of Pier 2.

The Contractor finished construction of the wall portion of the cast-in-place retaining wall on the south side of the bridge and is working to finish backfilling the Bridge Abutment B at the north side of the project.