Project Updates: August 10, 2021
The Harford Road Bridge contractor has set all the precast bridge panels. Base pavement has been placed on the [...]
Project Updates: July 16, 2021
The Harford Road Bridge contractor is setting the precast bridge panels. Grading is complete on the north side and [...]
Project Updates: June 4, 2021
The Harford Road Bridge contractor is completing work to pour an exterior piece of the concrete deck and the [...]
Project Updates: April 29, 2021
The Harford Road Bridge contractor continues work to pour an exterior piece of the concrete deck and the top [...]
Project Updates: April 8, 2021
The Harford Road Bridge contractor has removed the stream flow diversion structures and installed rip rap scour protection. They [...]
Project Updates: February 25, 2021
The Harford Road Bridge contractor has finished the approach slabs at each end of the deck and is working [...]