News & Updates

/News & Updates

Project Updates: November 14, 2019

The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation.  Both the north and south abutments are complete, and pier construction will begin in the coming months.

Retaining walls on the south side of the project are underway, and the pedestrian tunnel is fully installed and backfilled.

Drainage pipe has be installed around the project as well.

Additional images

2019-11-14T11:00:11-05:00November 14th, 2019|

Project Updates: September 23, 2019

The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. Phase 2 of the north and south abutments is underway, with an estimated completion date for the abutments being mid-October.

The proposed pedestrian tunnel is completely installed, with backfill and drainage currently being installed.

Excavation for a long mechanically stabilized earth wall at the south end of the project is uncomplete. Once drainage for this wall is installed, the wall construction will begin.

Additional images

2019-10-08T13:20:16-05:00October 8th, 2019|

Project Updates: August 26, 2019

The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. Phase 1 of the north abutment stem wall has been poured, while the first phase of the south abutment stem wall has been formed and will be poured by the end of the month. Additional walls for the bridge’s foundation continue to be formed and rebar installed.

The proposed pedestrian tunnel is completely installed, with backfill ready to be installed on top.

Excavation for a long mechanically stabilized earth wall at the south end of the project is underway.

Additional images

2019-08-27T08:02:13-05:00August 27th, 2019|

Project Updates: August 1, 2019

The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. The north abutment stem wall has been formed and is ready for concrete to be poured within the forms. The south abutment footing has been placed and the stem wall formwork has begun.

Excavation for the proposed pedestrian tunnel between Chesterfield Avenue and Herring Run has been completed. Footings for the pedestrian tunnel will be installed in early August.

Additional images

2019-08-01T15:49:49-05:00August 1st, 2019|

Harford Road and Lake Montebello Drive Closure

To prepare for constructing the proposed pedestrian tunnel, the Harford Road Bridge contractor plans to mobilize equipment and materials to the south end of the project this Monday, August 12th through Thursday, August 15th.

To accommodate this effort, Harford Road and Lake Montebello Drive in the vicinity of Chesterfield Avenue will be closed from 9AM to 3PM. Reference attached sketch.

Please consider using alternate routes on these days during the specified time frame.

2019-08-06T12:32:04-05:00July 15th, 2019|

Project Updates: July 2, 2019

The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. The north abutment footing has been placed, and reinforcement and formwork for the abutment wall is underway. The south footing formwork and reinforcement bar have been installed and are awaiting concrete.

Excavation for the two piers has been completed and construction of the pier footings will begin in July.

Excavation for the proposed pedestrian tunnel between Chesterfield Avenue and Herring Run is underway. Footings for the pedestrian tunnel will be installed in July.

Additional images

2019-07-08T11:18:59-05:00July 8th, 2019|

Project Updates: May 31, 2019

The Harford Road Bridge contractor has fully completed demolition of the existing bridge.  Excavation and rock removal for the new bridge abutments and piers is underway.

Construction of the north abutment will begin in early June, followed by construction of the south abutment later in the month.

The demolition shield above Herring Run is fully removed, and stockpiled material in the project’s southeast corner will be removed in June.

Additional images

2019-05-31T08:31:45-05:00May 31st, 2019|

Project Updates: May 1, 2019

The Harford Road Bridge contractor is nearly complete with demolition of the existing bridge.  The existing arches have been completely removed and the last remaining parts of concrete that were below ground are being excavated.  The rubble created by the demolition of the bridge is being pulverized and taken off site.

Rock excavation for the proposed north abutment substructure is underway.  The footing for this substructure is scheduled to be installed in mid-May.

The demolition shield above Herring Run is being removed, and stockpiled in the projects southeast corner is being removed.

2019-05-07T05:34:42-05:00May 1st, 2019|

Project Updates: April 11, 2019

The Harford Road Bridge contractor continues with the demolition of the bridge.  Earth fill that was once above the concrete arches has been removed and stockpiled nearby.  The northern-most span has been completely removed, while vertical walls above the arches for the south span and middle span have been removed.

Demolition of the bridge will continue over the next four weeks and the remaining concrete arches will be removed.  By the end of April, the existing Harford Road Bridge will no longer be present.

Stockpiled concrete demolition debris from the existing bridge will be crushed and reused as construction material elsewhere in the region.  Some of the recycled material will be used for the new Harford Road Bridge.

Other work performed around the site includes the installation of stormwater drainage piping, erosion and sediment control measures, and site security fencing.

2019-04-11T19:29:56-05:00April 11th, 2019|

Project Updates: March 15, 2019

The Harford Road Bridge contractor has begun demolishing activities for the existing bridge. Pavement across the new bridge has been removed, uncovering existing trolley tracks that once ran down Harford Road. The existing trolley tracks have been removed, along with existing sidewalk and bridge parapet. Retaining walls on the south end of the bridge have been demolished as well.

Demolition of the bridge will continue over the next eight weeks where various components of the bridge will come down systematically. Fill within the bridge will be excavated and removed, leaving the bridge concrete walls and arch exposed. Walls will then be removed, followed by the arches. A demolition shield has been installed over the creek to protect debris from entering the waterway.

Other work performed around the site includes installation of stormwater drainage piping, erosion and sediment control measures, and site security fencing.

2019-03-15T12:03:50-05:00March 15th, 2019|

Project Updates: February 22, 2019

The Harford Road Bridge contractor has begun to prepare for the demolition of the existing bridge by placing steel beams and timber matting over the waterway.  Once Verizon relocates existing telecommunications lines that run through the bridge, the contractor will begin removal of the existing structure.  This work is anticipated to begin on February 25, 2019.  Demolition will be performed by hydraulic hammers and heavy equipment, which will be one of the louder operations throughout the duration of the project.  The Herring Run Trail under the Harford Road Bridge will be completely closed for this stage of construction.  Demolition is expected to be complete in approximately 3 months.

In preparation for this phase of work, contractor hours will be adjusted in order to complete demolition activities in a more timely manner.  Starting February 25th, the contractor will begin working a schedule of 7am-7pm from Monday through Saturday.

The contractor is also continuing the installation of a sandbag stream diversion system.  This will allow for the construction of the proposed bridge piers without interference from the flowing waterway.

Other work being performed at this time includes the installation of stormwater drainage piping, erosion and sediment control measures, and site security fencing.

2019-02-22T14:00:49-05:00February 22nd, 2019|