Harford Road and Lake Montebello Drive Closure

To prepare for constructing the proposed pedestrian tunnel, the Harford Road Bridge contractor plans to mobilize equipment and materials to the south end of the project this Monday, July 29th through Wednesday July 31st.

To accommodate this effort, Harford Road and Lake Montebello Drive in the vicinity of Chesterfield Avenue will be closed from 9AM to 3PM. Reference attached sketch.

Please consider using alternate routes on these days during the specified time frame.

2019-07-17T15:44:33-04:00July 15th, 2019|

Project Updates: July 2, 2019

The Harford Road Bridge contractor continues to move forward with the construction of the new bridge’s foundation. The north abutment footing has been placed, and reinforcement and formwork for the abutment wall is underway. The south footing formwork and reinforcement bar have been installed and are awaiting concrete.

Excavation for the two piers has been completed and construction of the pier footings will begin in July.

Excavation for the proposed pedestrian tunnel between Chesterfield Avenue and Herring Run is underway. Footings for the pedestrian tunnel will be installed in July.